﻿<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Journal Archiving and Interchange DTD with MathML3 v1.2 20190208//EN" "http://dtd.nlm.nih.gov/publishing/3.0/journalpublishing3.dtd">
<article
    xmlns:mml="http://www.w3.org/1998/Math/MathML"
    xmlns:xlink="http://www.w3.org/1999/xlink" dtd-version="3.0" xml:lang="en" article-type="review-article">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">JAIBD</journal-id>
      <journal-title-group>
        <journal-title>Journal of Artificial Intelligence and Big Data</journal-title>
      </journal-title-group>
      <issn pub-type="epub">2771-2389</issn>
      <issn pub-type="ppub"></issn>
      <publisher>
        <publisher-name>Science Publications</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.31586/jaibd.2023.1386</article-id>
      <article-id pub-id-type="publisher-id">JAIBD-1386</article-id>
      <article-categories>
        <subj-group subj-group-type="heading">
          <subject>Review Article</subject>
        </subj-group>
      </article-categories>
      <title-group>
        <article-title>
          A Survey of Machine Learning Use Cases (Applications) in Project Planning and Scheduling Process
        </article-title>
      </title-group>
      <contrib-group>
<contrib contrib-type="author">
<name>
<surname>Syed</surname>
<given-names>Muzaffer Hussain</given-names>
</name>
<xref rid="af1" ref-type="aff">1</xref>
<xref rid="cr1" ref-type="corresp">*</xref>
</contrib>
<contrib contrib-type="author">
<name>
<surname>Ragireddy</surname>
<given-names>Uday Kumar</given-names>
</name>
<xref rid="af2" ref-type="aff">2</xref>
</contrib>
<contrib contrib-type="author">
<name>
<surname>Addepalli</surname>
<given-names>Prasanth Varma</given-names>
</name>
<xref rid="af3" ref-type="aff">3</xref>
</contrib>
<contrib contrib-type="author">
<name>
<surname>Bandaru</surname>
<given-names>Sridhar Reddy</given-names>
</name>
<xref rid="af4" ref-type="aff">4</xref>
</contrib>
<contrib contrib-type="author">
<name>
<surname>Shyam</surname>
<given-names>Dhuli</given-names>
</name>
<xref rid="af5" ref-type="aff">5</xref>
</contrib>
<contrib contrib-type="author">
<name>
<surname>Manoharan</surname>
<given-names>Prabu</given-names>
</name>
<xref rid="af6" ref-type="aff">6</xref>
</contrib>
      </contrib-group>
<aff id="af1"><label>1</label> IT Project Lead, Vdrive IT Solutions Inc, USA</aff>
<aff id="af2"><label>2</label> Vdrive IT Solutions, Inc, Richardson, Texas, USA</aff>
<aff id="af3"><label>3</label> Federal Motor Carrier Safety Administration, Atlanta, Georgia, USA</aff>
<aff id="af4"><label>4</label> Program Management, IT, Microsoft, USA</aff>
<aff id="af5"><label>5</label> Business Application, IT, Nagase Holdings America Corp, USA</aff>
<aff id="af6"><label>6</label> Information Technology, Bourns Inc, USA</aff>
<author-notes>
<corresp id="c1">
<label>*</label>Corresponding author at: IT Project Lead, Vdrive IT Solutions Inc, USA
</corresp>
</author-notes>
      <pub-date pub-type="epub">
        <day>27</day>
        <month>12</month>
        <year>2023</year>
      </pub-date>
      <volume>3</volume>
      <issue>1</issue>
      <history>
        <date date-type="received">
          <day>22</day>
          <month>09</month>
          <year>2023</year>
        </date>
        <date date-type="rev-recd">
          <day>21</day>
          <month>11</month>
          <year>2023</year>
        </date>
        <date date-type="accepted">
          <day>12</day>
          <month>12</month>
          <year>2023</year>
        </date>
        <date date-type="pub">
          <day>27</day>
          <month>12</month>
          <year>2023</year>
        </date>
      </history>
      <permissions>
        <copyright-statement>&#xa9; Copyright 2023 by authors and Trend Research Publishing Inc. </copyright-statement>
        <copyright-year>2023</copyright-year>
        <license license-type="open-access" xlink:href="http://creativecommons.org/licenses/by/4.0/">
          <license-p>This work is licensed under the Creative Commons Attribution International License (CC BY). http://creativecommons.org/licenses/by/4.0/</license-p>
        </license>
      </permissions>
      <abstract>
        The swift changes in the complexity of the project, scarcity of resources, and pressure on the organization have demonstrated the necessity of more intelligent and data-driven planning and scheduling methods. Conventional methods tend to be less effective in the tasks of uncertainty management, dynamic environment, and dynamism of the project ecosystems of the modern world. The application of machine learning (ML) in the planning and scheduling of projects is thoroughly reviewed in this paper, and it is evident that ML may help to improve the accuracy of forecasts, optimize resource distribution, and make decisions. This paper offers an analysis of the basic concepts of project management, evidence-based practices, and how supervised and unsupervised learning, as well as reinforcement learning concepts, can be combined in the scheduling process. Furthermore, the new literatures are examined to bring out new techniques, including predictive modelling, optimization algorithms, simulation-based planning and adaptive scheduling models. The review determines the main strengths, weaknesses, and gaps in the research that impact the adoption of ML-driven approaches. All in all, the paper describes the ways in which machine learning technologies can change the traditional way of project management by creating efficient, resilient, and proactive planning systems.
      </abstract>
      <kwd-group>
        <kwd-group><kwd>Project Management</kwd>
<kwd>Project Planning</kwd>
<kwd>Project Scheduling Process</kwd>
<kwd>Artificial Intelligence (AI)</kwd>
<kwd>Machine Learning (ML)</kwd>
</kwd-group>
      </kwd-group>
    </article-meta>
  </front>
  <body>
    <sec id="sec1">
<title>Introduction</title><p>The world is always changing, and businesses need to be able to quickly respond to projects that help them reach their goals. To do this, they need to be able to handle the project well so that it meets its goals and is completed on time and on budget. In project acceptable management, the goal is to plan and control the creation of an acceptable system within a given time frame and at a minimum cost [
<xref ref-type="bibr" rid="R1">1</xref>]. Uncontrolled changes in project scope, delays in delivery, cost overruns, and unmet or unknown needs are all results of poor project management. Everyone and everything associated with the project feels the effects of delays. Delaying the project's launch would make it harder to get the anticipated revenue and drive-up financial expenses, which is particularly problematic for the owner's company. Furthermore, the owner could encounter many additional challenges stemming from the obligations assumed in relation to the contract's specified delivery date [
<xref ref-type="bibr" rid="R2">2</xref>]. Cost overruns are a common problem for contractors when project execution times are extended. This is because there are several factors that contribute to these overruns, such as increased spending on management staff, higher material costs, higher finance costs, contract penalties, and so on. In addition, contractors whose projects are late may have their reputations damaged and their ability to secure new contracts hindered, due to the typical competitive atmosphere in the construction sector [
<xref ref-type="bibr" rid="R3">3</xref>].</p>
<p>The goal of project planning and scheduling is to complete tasks in accordance with the project schedule as intended, and if there are any delays, the process can be adjusted accordingly. Since time is associated with every aspect of a project, whether directly or indirectly, controlling it means controlling the entire planning system [
<xref ref-type="bibr" rid="R4">4</xref>]. Alternatively, it can be said to be the act of organizing, guiding, and regulating resources, protocols, and procedures to accomplish predetermined objectives in solving every day or scientific problems [
<xref ref-type="bibr" rid="R5">5</xref>]. The most common, but not exclusive, purposes and objectives of projects are to bring about positive change or increase value. Projects are ad hoc endeavors with beginnings and endings, and they typically have particular deliverables, time constraints, and budget constraints. Projects tend to have a shorter duration than operations, which are more permanent or semi-permanent functional activities that produce goods or services. Project planning and control are cornerstones of project management. Tasks including project scheduling, status reporting, baseline plan comparison, deviation analysis, out-of-control scenario discovery, and suitable corrective action taking involve a myriad of choice concerns [
<xref ref-type="bibr" rid="R6">6</xref>]. In response to these decision-making challenges, numerous approaches, methodologies, and resources have emerged during the past few decades.</p>
<p>Artificial intelligence (AI) refers to a computer's or machine's capacity to solve difficult and complicated tasks. The merging of information technology with physiological intelligence has led to computerized artificial intelligence, which can be utilized to accomplish objectives [
<xref ref-type="bibr" rid="R7">7</xref>]. Massive increases in computing capacity, advances in AI techniques (such as DL), and the proliferation of massive data are driving forces behind the emergence of AI and ML [
<xref ref-type="bibr" rid="R8">8</xref>]. Due to the widespread use of software, there is a wealth of data available regarding software projects that can be used by AI approaches [
<xref ref-type="bibr" rid="R9">9</xref>]. AI transform software project management in many ways, in my opinion. It automates mundane administrative tasks, improve project planning, streamline analytics-driven risk assessments and predictions, and offer practical recommendations.</p>
<title>Structure of the Paper</title><p>The paper follows the following structure: Section II gives the major terms in the project planning and scheduling. Section III states about data-driven approaches and methods of analysis. In Section IV, the author explores ML methods that can be used in planning and scheduling. Section V is the review of recent literature and key findings. Section VI includes the conclusion and the future research directions.</p>
</sec><sec id="sec2">
<title>Project Planning and Scheduling</title><p>A number of resources (human and financial, physical and digital, and ancillary) inside a single company come together in a project to accomplish its goals. Project planning entails looking ahead to current tasks and conditions, establishing goals and objectives, and deciding on policies, programs, a timeline, a power source, an operational budget, and a procedure for implementing the project's policies and procedures [
<xref ref-type="bibr" rid="R10">10</xref>]. Project scheduling is the process of figuring out how long certain tasks, resources, and activities within a project take to finish.</p>
<title>2.1. Core Concepts of Project Planning</title><p>The completion of a project within the allotted time and money, as well as its performance meeting or exceeding expectations set out in the original plan, constitute its success. Thus, preparation is key to a project's overall success. All of these projects, as illustrated inFigure <xref ref-type="fig" rid="fig1"> 1</xref>, have distinct stages that, when completed, determine the total amount of work and the extent to which they affect the project's success. A project's planning phase is among its most important components [
<xref ref-type="bibr" rid="R11">11</xref>]. Although numerous elements have been explored in previous research, one of the most essential ones is planning. Prior studies have shown that inadequate planning is a contributing factor to project failure.</p>
<fig id="fig1">
<label>Figure 1</label>
<caption>
<p>Concepts of Project Planning and Scheduling</p>
</caption>
<graphic xlink:href="1386.fig.001" />
</fig><title>2.1.1. Project objectives and constraints</title><p>The importance of time, money, and quality as project success factors has led to their widespread adoption as metrics for monitoring project status. The need of resolving disputes or compromises among the project's objectives was recognized by managers as crucial to the project's successful management [
<xref ref-type="bibr" rid="R12">12</xref>]. In understanding this necessity, the projects are usually being limited by the lack of resources, deadlines, and predetermined costs, which directly affects the decision-making. Project goals cannot be achieved due to the insurmountable balancing act between these constraints and the constant pressure to satisfy stakeholders' expectations and performance requirements.</p>
<title>2.1.2. Work Breakdown Structure (WBS)</title><p>Project scope is defined by the end results, and the Work Breakdown Structure (WBS) is a method for organizing those results into manageable chunks. Work breakdown structures (WBSs) are useful for organizing and defining project scopes because they group the various work components of a project according to their product orientation. In order to illustrate the logical connections between different parts of a project, a hierarchical framework called a Work Breakdown Structure (WBS) can be useful [
<xref ref-type="bibr" rid="R13">13</xref>]. At each stage, a project component is further specified and split. Its primary function is to design, assign, and monitor the scope of individual tasks at various points in a project's lifetime. All of the project's actions are bound together by its structure and code. It is guaranteed that each control account has its own unique WBS element by meticulously establishing the WBS.</p>
<title>2.1.3. Resource and Cost Planning</title><p>A project's cost variances defined as any changes to the budget or actual costs are a major factor in the project's cost performance. During the comprehensive planning stage, the design, specs, scope, and final cost are created. An alternative method for estimating the potential range of costs is to use the award of contract, which is the final, agreed-upon price at the outset of the construction process [
<xref ref-type="bibr" rid="R14">14</xref>]. The interplay between the several subprocesses that make up project cost management, including planning, estimating, budgeting, financing, managing, and controlling expenses is essential to completing a project within the allotted budget.</p>
<title>2.2. Project Scheduling Techniques and Practices</title><p>The software manager's workload is heavy, and one of the most taxing responsibilities is project scheduling. Distribution of estimated effort across the planned period of a project is accomplished by this activity, which involves assigning that effort to specific engineering tasks.  Project scheduling, in its simplest form, is the process of dividing a large project into smaller tasks and approximating the time required to finish each one [
<xref ref-type="bibr" rid="R15">15</xref>]. In addition, managers are tasked with estimating the resources that required to finish each mission. Faster problem detection, time savings, consistency building, increased visibility, problem resolution, and countless other benefits are all part of software project scheduling.Figure <xref ref-type="fig" rid="fig2"> 2</xref> shows an example of the standard project scheduling diagrams that include the Work Breakdown Structure (WBS), activity dependencies, and personnel allocation. The following is a list of some of the various methods to schedule software projects.</p>
<fig id="fig2">
<label>Figure 2</label>
<caption>
<p><b> </b>Project Scheduling Techniques</p>
</caption>
<graphic xlink:href="1386.fig.002" />
</fig><title>2.2.1. CPM and PERT Techniques</title><p>A deterministic decision-support system (DSS), Critical Path Method (CPM) and the Project Evaluation and Review Technique (PERT) were the forerunners of computerized project management. Contrarily, PERT is all about creating and overseeing project timelines in situations where there is a lot of unpredictability [
<xref ref-type="bibr" rid="R16">16</xref>]. An approach to stochastic analysis is what its engine is based on.  Processing times and budget consumption can be very unpredictable in different project setups, according to many sources. In order to entice buyers, it also guarantees performance criteria. Appropriate planning and scheduling of major projects makes use of both the CPM and the PERT [
<xref ref-type="bibr" rid="R17">17</xref>].  As a result, project managers are better able to track how each phase is progressing. The main distinction is that CPM uses deterministic durations to plan the tasks.</p>
<title>2.2.2. Resource Allocation</title><p>The purpose of resource allocation is to distribute available resources in a cost-effective manner. It incorporates the principles of managing resources. Allotting resources in project management entails planning tasks and the resources needed to complete them within the constraints of the project timeline and the available resources [
<xref ref-type="bibr" rid="R18">18</xref>]. The project schedule is a useful tool for communicating the tasks that need to be done, the resources that assigned to those tasks, and the deadlines for those executions.  To complete the project on time, the timeline must include all activities.</p>
<title>2.2.3. EVM Monitoring</title><p>The most critical way to keep an eye on a project's status is to compare it to the plan and note the discrepancy. To do this, can compute a number of indices, including critical ratios (CR), performance indices, and performance variances. The EVM is a foolproof way to manage a project's success. The time, money, and production progress of a project can be better reported by comparing the actual results to the anticipated and budgeted ones [
<xref ref-type="bibr" rid="R19">19</xref>]. The three primary requirements of EVM are anticipated budget for work scheduled (BCWS), actual budget for work performed (BCWP), and actual cost for work completed (ACWP).</p>
</sec><sec id="sec3">
<title>Data-Driven Methods for Project Planning and Scheduling</title><p>Project managers may plan, track, and control projects with data-driven management, ensuring they are completed on time and under budget. Data may aid professionals in making more informed judgments; this much is obvious. For instance, risk analysis and knowing what to do when uncertainty threatens a project both require data analysis [
<xref ref-type="bibr" rid="R20">20</xref>]. It's all about making smarter decisions using data. In the absence of evidence, "you're just another person with an opinion," as Edward Deming put it. Integrating the two approaches is the goal of data-driven project management: As projects progress, make better decisions by combining facts (data) with experience (opinions).</p>
<title>3.1. Data Collection and Analysis in Project Management</title><p>Shipment and examination of data within the project management entail collecting correct project data and converting the data into practical information that aids planning as well as decision-making. Good data practices maintain credible documentation of project activity, resources, project schedule, and performance measures seeFigure <xref ref-type="fig" rid="fig3"> 3</xref>. The companies can determine patterns, determine risks, and increase forecast accuracy by using the historical and real-time data of projects. A more efficient project schedule and planning process can be achieved with this analytical foundation.</p>
<fig id="fig3">
<label>Figure 3</label>
<caption>
<p><b> </b>Data Analysis Concepts of any Project</p>
</caption>
<graphic xlink:href="1386.fig.003" />
</fig><title>3.1.2. Project Data Sources and Quality</title><p>Data quality concerns may be a major motivator for sharing and curating data. Concerns over data quality, abuse, or misunderstanding can arise for data owners. On the flip side, users might be hesitant to trust or even refuse to use the data due to a lack of knowledge about or access to the procedures that created it [
<xref ref-type="bibr" rid="R21">21</xref>]. Decisions and discoveries are only as good as the data used to make them.  In order to make good decisions or to defend, verify, and assess past choices and outcomes, it is crucial to have access to high-quality data for the long haul. The same data or metadata might have varying degrees of value in different activities and at different periods, and it can be used for multiple purposes; this is known as the data lifecycle. For research to be repeatable, process-level analysis of data, metadata, and data quality assurance is required. </p>
<title>3.1.3. Historical Data Analysis for Planning</title><p>There is a significant skill gap when it comes to operating computerized data systems, which makes it hard to gather and organize data. This is because projects are evaluated primarily on qualities such as site experience and know-how, rather than computer skills. To address these issues, it is necessary to enhance the system for managing historical data in order to extract ineffective factors. Therefore, it is necessary to merge the departments responsible for data management. Data accumulation is the primary emphasis of the examination and analysis of a domestic company's historical data, as illustrated inFigure <xref ref-type="fig" rid="fig4"> 4</xref>. This survey makes it clear that there is a vast amount of historical data kept in a cabinet and that each field uses its own unique system for document classification. The primary means of data transmission between the headquarters and the fields, as well as between individual fields, are facsimile machines and electronic mail.</p>
<fig id="fig4">
<label>Figure 4</label>
<caption>
<p><b> </b>Historical Data Frequency</p>
</caption>
<graphic xlink:href="1386.fig.004" />
</fig><title>3.2. Predictive and Decision-Support Methods</title><p>Predictive and decision-support approaches make use of analytical models to determine the outcomes of a project, and inform decision-makers (planners) on informed decisions. Such methods involve historical data, performance trends, and calculations to approximate activity durations, cost and possible schedule risks. Project managers might assess various timeline scenarios, optimize resource use, and anticipate bottlenecks with the help of forecasting tools and decision support systems. Project planning and scheduling are made more precise, adaptable, and efficient with the help of these methods.</p>
<title>3.2.1. Forecasting project performance</title><p>The conventional method for managing a project is keeping tabs on actual performance, comparing it to anticipated performance, analyzing the difference, and finally, forecasting the outcomes that dictated by management's actions [
<xref ref-type="bibr" rid="R22">22</xref>]. Performance indicators, such the schedule performance index (SPI) and the cost performance index (CPI), change throughout a normal project. During the initial stages of a project, the management may face challenges or encounter poor performance. Therefore, the project's performance in the subsequent reporting period(s) is not static and identical to the previous one, but rather it is adaptable, changing, and influenced by the previous one.</p>
<title>3.2.2. Data-driven scheduling and optimization</title><p>Practical researchers are showing a lot of interest in the RCPSP. Taking into account the resource needs and the precedence linkages between tasks is an important part of project scheduling.  For instance, the academic topic has numerous applicable real-world counterparts in the construction and consulting industries, leading to a difficult list of cases with different optimization goals. Autonomous agents for scheduling projects in multiple modes Learning agents for the multi-mode project scheduling problem. The MRCPSP is a more generalized form of the RCPSP; for instance, it would take six days for two people to dig a hole with shovels alone, but just two days with four people plus an additional barrow [
<xref ref-type="bibr" rid="R23">23</xref>]. Both the RCPSP and its generalization, the MRCPSP, are proven to be NP-hard optimization problems.</p>
</sec><sec id="sec4">
<title>Machine Learning Techniques for Project Planning and Scheduling</title><p>The goal of ML, a subfield of computer science, is to enable computers to learn automatically, without the need for human intervention. Project planning and scheduling rely on a set of analytical techniques and processes designed to organize activities, allocate resources, and control project timelines effectively ML techniques are divided in three approaches: Supervised learning, unsupervised learning and Reinforcement learning as shown inFigure <xref ref-type="fig" rid="fig5"> 5</xref>. There are modern planning systems that combine computational tools that assist in the sequencing of activities, coordination of resources and monitoring of performances. ML as a sophisticated direction of artificial intelligence helps in this field of research because it allows predicting and making decisions based on data [
<xref ref-type="bibr" rid="R24">24</xref>]. Intimately connected with computational statistics, ML offers the models that can predict the project durations, costs, and risks. Its close relationship with mathematical optimization also maximizes the efficacy of the scheduling because it provides tools and models of better resource allocation and project delays reduction.</p>
<fig id="fig5">
<label>Figure 5</label>
<caption>
<p><b> </b>Machine Learning Techniques</p>
</caption>
<graphic xlink:href="1386.fig.005" />
</fig><title>4.1. Supervised Learning</title><p>Training an AI model with accurate classifications on a subset of a data source enables supervised learning to discover hidden correlations and patterns in the full dataset. The objective of learning process is to come up with a model that can make correct predictions on new real-life data. Supervised learning involves the use of ground-truth data to receive a model of the relationship between inputs and outputs and the labeled datasets are the point of reference of this mapping. After training, the model uses the relationships learnt to make predictions on new, unseen data [
<xref ref-type="bibr" rid="R25">25</xref>]. Supervised learning is also extensively applied in project planning and scheduling to predict the duration of the activities, the cost of the project, and schedule risks of a project with the help of historical project data. Such forecasts enable project managers to come up with more precise schedules and enhance decision-making pertaining to the allocation of resources and optimization of schedules.</p>
<title>4.2. Unsupervised Learning</title><p>Unsupervised ML approaches allow one to analyze raw data and produce meaningful insights on unlabeled datasets simpler. The development of factor analysis, latent models, hierarchical learning, clustering schemes and outlier detection have immensely contributed to the ability of unsupervised learning. Recent progress [
<xref ref-type="bibr" rid="R26">26</xref>], such as the use of DL as an unsupervised method, is another advancement that enhances the field by allowing automated identification of patterns without a lot of feature engineering or domain-specific processing. These methods play a useful role in the process of project planning and project scheduling to determine the existence of hidden patterns in the project performance data, grouping similar activities of the project and identifying of irregularities or inefficiency in the resources. These insights can aid better decision-making when it comes to the planning processes and assist organizations in identifying systemic problems that can influence the future project timelines.</p>
<title>4.3. Reinforcement Learning</title><p>RL is a ML paradigm where an autonomous agent learns the act of making decisions by interacting with the environment as well as being given feedback in terms of rewards or penalties. Rather than using labeled data, RL refines its strategy via trial error, and over time it finds actions that result in cumulative reward being maximized [
<xref ref-type="bibr" rid="R27">27</xref>], This method is especially effective when operating in sequential decision-making problems, where the results of an action are sensitive to the dynamics of the environment, as well as the long-term consequences of its action. Applications of RL techniques in project planning and scheduling include optimization of activity sequencing, resource allocation where limited resources are used and schedule adjustments to project uncertainties like delays or cost change. Learning the best policies with time helps the RL-based systems be more adaptive and efficient in the process of project management, as project planners are able to test other scheduling alternatives and react to the evolving project conditions proactively.</p>
</sec><sec id="sec5">
<title>Literature Review</title><p>The above literature review indicates that determining and ranking critical success factors is an important step in enhancing the outcomes of projects and decision-making. Nevertheless, most of the studies are constrained by the small sample sizes, limited external validity, and the use of subjective ways of evaluation.</p>
<p>Wang et al. (2019) released a sub-model for proactive scheduling of several projects. Reactive scheduling incorporates the proactive scheduling scheme as its baseline scheduling scheme in the case that the activity is discontinued. To meet this need, propose a genetic simulated annealing method that, when applied to the provided model, can provide several scheduling options. Using a buffer change operator (SC) and a crossover operator, a genetic simulated annealing approach is built to guarantee the early generation and protection of an ideal individual [
<xref ref-type="bibr" rid="R28">28</xref>].</p>
<p>Shimoda, Wilairath and Kounosu (2019) Project operations are viewed as a two-tiered structure comprising of value realization and means realization; this is what defines the suggested method. Thus, the nine parts of the project activity are an amalgamation of the five V-model steps for means realization and the five PMBOK process groups for value realization. The proposed approach avoids a major scope creep while creating WBS, and studies done by college students show that even novices can grasp it with ease [
<xref ref-type="bibr" rid="R29">29</xref>].</p>
<p>Zachko and Kobylkin (2018) The proposed approach is grounded on the theory's basic principles, and its practical use in studying the effectiveness of people's mass evacuation is proven. Throughout the simulation, used new methods, including one to mimic the object's operational life cycle with a big number of people on board and another to simulate an event&#x26;#x02014;the object's evacuation due to a notice of substitution&#x26;#x02014;throughout. The use of simulation modeling tools built on the Anylogic multi-agent modeling environment classes allowed us to see the project management process in action [
<xref ref-type="bibr" rid="R30">30</xref>].</p>
<p>Kusturica et al. (2018) discussed various concepts from the SimCast research project, which is a collaboration between the Kassel and Zwickau universities. During project planning, it seeks to provide a technique for task duration estimation. Based on the researched state-of-the-art, the requirements, planning process, and present technical infrastructure of the predicted modular prototype are outlined. The project management process may already be benefiting from the first plug-ins that have been introduced [
<xref ref-type="bibr" rid="R31">31</xref>].</p>
<p>Hameed et al. (2017) Previous issues with scheduling and personnel were the primary focus of the solution-finding process. Suggested an approach that involves optimizing particle swarms. For project managers, the proposed algorithm is illustrative of activities related to personnel and scheduling. Domain or problem type-specific efficient management plan creation is the algorithm's primary goal.  The most efficient and economical method for achieving a complete and ideal project timeline is also shown [
<xref ref-type="bibr" rid="R32">32</xref>].</p>
<p>Rihm and Trautmann (2017) constructed a novel MILP model based on explicit assignment and sequencing variables; enhanced the model's performance by excluding certain symmetric solutions from the search space and modifying the sequencing limits to account for incompatible activity pairings. For four common literature test sets, this one-of-a-kind model outperforms two state-of-the-art models in the constrained resource situation [
<xref ref-type="bibr" rid="R33">33</xref>].</p>
<p>Peralta et al. (2016) provided multiple examples of the time record as outlined in the Personal Software Process. Both managers and employees benefit from the study, which yields a set of notes and suggestions for handling different kinds of work and scheduling in different contexts [
<xref ref-type="bibr" rid="R34">34</xref>].</p>
<p>Table 1 is a summary of the previous studies on project scheduling and planning, including research objectives, research methods, main findings, and research constraints. The results validate the performance gains by the use of modern models, but also expose typical limitations in terms of reduced validation, scalability and context-specific validity.</p>
<table-wrap id="tab1">
<label>Table 1</label>
<caption>
<p><b>Table </b><b>1</b><b>.</b><b> </b><b>Summary of Recent Studies on Project Scheduling, Planning, and Optimization Approaches</b></p>
</caption>

<table>
<thead>
<tr>
<th align="center"><bold>Reference</bold></th>
<th align="center"><bold>Study  on</bold></th>
<th align="center"><bold>Approach</bold></th>
<th align="center"><bold>Key  Findings</bold></th>
<th align="center"><bold>Challenges  / Limitations</bold></th>
<th align="center"><bold>Future  Directions</bold></th>
<th align="center"></th>
</tr>
</thead>
<tbody>
<tr>
<td align="center">Wang et al. (2019)</td>
<td align="center">Proactive and reactive  multi-project scheduling</td>
<td align="center">An approach for genetic  simulated annealing that incorporates proactive scheduling into reactive  scheduling and makes use of buffer change and crossover operators</td>
<td align="center">Generates alternative  schedules efficiently and protects optimal solutions in early algorithm stages</td>
<td align="center">Computational complexity  and dependency on algorithm parameter tuning</td>
<td align="center">Enhancement of algorithm  scalability and application to real-time dynamic project environments</td>
<td align="center"></td>
</tr>
<tr>
<td align="center">Shimoda, Wilairath &#x00026;  Kounosu (2019)</td>
<td align="center">Work Breakdown Structure  (WBS) creation</td>
<td align="center">Two-layer activity  structure combining PMBOK process groups and V-model steps</td>
<td align="center">Improves beginner  understanding and reduces scope loss in WBS creation</td>
<td align="center">Validation mainly limited  to student-based experiments</td>
<td align="center">Application in  industrial-scale projects and empirical validation with experienced project  managers</td>
<td align="center"></td>
</tr>
<tr>
<td align="center">Zachko &#x00026; Kobylkin  (2018)</td>
<td align="center">Evacuation efficiency in  mass-occupancy facilities</td>
<td align="center">Simulation modeling using  AnyLogic multi-agent environment and event-based evacuation scenarios</td>
<td align="center">Enables visualization and  efficiency analysis of evacuation processes</td>
<td align="center">Focused on specific  evacuation scenarios and infrastructure types</td>
<td align="center">Extension to broader  emergency scenarios and integration with real-time sensor data</td>
<td align="center"></td>
</tr>
<tr>
<td align="center">Kusturica et al. (2018)</td>
<td align="center">Project task duration  estimation</td>
<td align="center">Modular prototype with  plug-ins based on state-of-the-art planning processes</td>
<td align="center">Demonstrates potential  benefits for improving project duration estimation accuracy</td>
<td align="center">Prototype-level  implementation with limited empirical evaluation</td>
<td align="center">Full-scale deployment and  validation across diverse project domains</td>
<td align="center"></td>
</tr>
<tr>
<td align="center">Hameed et al. (2017)</td>
<td align="center">Staffing and scheduling  optimization</td>
<td align="center">Particle Swarm  Optimization (PSO)-based scheduling and staffing model</td>
<td align="center">Produces cost-effective  and efficient project schedules</td>
<td align="center">Performance sensitive to  problem domain characteristics</td>
<td align="center">Hybrid optimization  techniques and real-world case study validation</td>
<td align="center"></td>
</tr>
<tr>
<td align="center">Rihm &#x00026; Trautmann  (2017)</td>
<td align="center">Resource-constrained  project scheduling</td>
<td align="center">Novel MILP model with  improved assignment and sequencing constraints</td>
<td align="center">Outperforms existing  models, especially under scarce resource conditions</td>
<td align="center">Increased model complexity  for large-scale instances</td>
<td align="center">Further optimization for  large datasets and integration with heuristic methods</td>
<td align="center"></td>
</tr>
<tr>
<td align="center">Peralta et al. (2016)</td>
<td align="center">Time and schedule  management</td>
<td align="center">Analysis of Personal  Software Process (PSP) time records</td>
<td align="center">Provides actionable  recommendations for employee and manager schedule management</td>
<td align="center">Context-specific findings  tied to PSP adoption</td>
<td align="center">Adaptation to agile and  hybrid project management frameworks</td>
<td align="center"></td>
</tr>
</tbody>
</table>
</table-wrap></sec><sec id="sec6">
<title>Conclusion and Future Work</title><p>An environment of growing uncertainty, increased project size and the desire to make critical decisions is a driving force behind the need to develop more sophisticated planning and scheduling tools. The conventional methods of project management cannot be used alone to ensure performance, particularly in dynamic and resource-based situations. The paper has done a comprehensive survey of the ML-based techniques of planning and scheduling of a project and has revealed itself to be useful in enhancing the forecasting, optimization of resources, and mitigation of risks. The literature synthesis reveals that supervised learning is a more effective predictor of costs and time, unsupervised learning uncovers concealed patterns and reinforcement learning can help in adaptive scheduling to evolving conditions. Despite the apparent opportunities of the ML-driven solutions, their use is still challenged by data quality, complexity of the model and lack of real-world validation. However, it is true that the results prove the effectiveness of the promising approach to using ML in combination with traditional planning tools to enhance project performance and operational resilience.</p>
<p>The research work that must be carried out in the future is the creation of scalable ML models that can work in real-time project contexts and can deal with heterogeneous data sources. The combination of ML and simulation, digital twins, and optimization models could also increase the predictive accuracy and the ability to schedule dynamically. Also, there is need to have wider empirical validation in many industries to determine generalizability. Enhancing data control, standardization and model interpretability will also be necessary to bring about reliable and industry-wide usage.</p>
</sec>
  </body>
  <back>
    <ref-list>
      <title>References</title>
      
<ref id="R1">
<label>[1]</label>
<mixed-citation publication-type="other">J. L. Leal, J. P. Rodr&#x000ed;guez, and O. A. Gallardo, "Project time: Time management method for software development projects-analytical summary," J. Phys. Conf. Ser., vol. 1126, Nov. 2018, doi: 10.1088/1742-6596/1126/1/012030.
</mixed-citation>
</ref>
<ref id="R2">
<label>[2]</label>
<mixed-citation publication-type="other">R. G. Sol&#x000ed;s-Carca&#x000f1;o, G. A. Corona-Su&#x000e1;rez, and A. J. Garc&#x000ed;a-Ibarra, "The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico," J. Constr. Eng., pp. 1-9, Oct. 2015, doi: 10.1155/2015/868479.
</mixed-citation>
</ref>
<ref id="R3">
<label>[3]</label>
<mixed-citation publication-type="other">P. L. Sharma, S. Gupta, and N. Dhiman, "Construction of Maximum Distance Separable Rhotrices using Cauchy Rhotrices over Finite Fields," Int. J. Comput. Appl., vol. 168, no. 9, pp. 8-17, Jun. 2017, doi: 10.5120/ijca2017914489.
</mixed-citation>
</ref>
<ref id="R4">
<label>[4]</label>
<mixed-citation publication-type="other">J. Sharanyasreenivas, G. Gajalakshmi, and K. R. Theja, "Project Planning, Scheduling and Preparation of Quality Assurance Control Documents," Int. Res. J. Eng. Technol., vol. 4, no. 11, pp. 1862-1869, 2017.
</mixed-citation>
</ref>
<ref id="R5">
<label>[5]</label>
<mixed-citation publication-type="other">P. M. Wale, N. D. Jain, N. R. Godhani, S. R. Beniwal, and A. A. Mir, "Planning and Scheduling of Project using Microsoft Project ( Case Study of a building in India )," IOSR J. Mech. Civ. Eng., vol. 12, no. 3, pp. 57-63, 2015.
</mixed-citation>
</ref>
<ref id="R6">
<label>[6]</label>
<mixed-citation publication-type="other">R. Pellerin and N. Perrier, "A review of methods, techniques and tools for project planning and control," Int. J. Prod. Res., vol. 57, no. 7, pp. 2160-2178, Apr. 2019, doi: 10.1080/00207543.2018.1524168.
</mixed-citation>
</ref>
<ref id="R7">
<label>[7]</label>
<mixed-citation publication-type="other">P. V&#x000e4;h&#x000e4;kainu and M. Lehto, "Artificial intelligence in the cyber security environment Artificial intelligence in the cyber security environment," in The 14th International Conference on Cyber Warfare and Security ICCWS2019, 2019, pp. 431-440.
</mixed-citation>
</ref>
<ref id="R8">
<label>[8]</label>
<mixed-citation publication-type="other">S. Garg, "AI/ML Driven Proactive Performance Monitoring, Resource Allocation and Effective Cost Management in SAAS Operations," Int. J. Core Eng. Manag., vol. 6, no. 6, pp. 263-273, 2019.
</mixed-citation>
</ref>
<ref id="R9">
<label>[9]</label>
<mixed-citation publication-type="other">H. K. Dam, T. Tran, J. Grundy, A. Ghose, and Y. Kamei, "Towards Effective AI-Powered Agile Project Management," in 2019 IEEE/ACM 41st International Conference on Software Engineering: New Ideas and Emerging Results (ICSE-NIER), IEEE, May 2019, pp. 41-44. doi: 10.1109/ICSE-NIER.2019.00019.
</mixed-citation>
</ref>
<ref id="R10">
<label>[10]</label>
<mixed-citation publication-type="other">S. Atin and R. Lubis, "Implementation of Critical Path Method in Project Planning and Scheduling," IOP Conf. Ser. Mater. Sci. Eng., vol. 662, p. 22031, 2019, doi: 10.1088/1757-899X/662/2/022031.
</mixed-citation>
</ref>
<ref id="R11">
<label>[11]</label>
<mixed-citation publication-type="other">T. Woldassilasie, E. Berhan, and B. Beshah, "Key project planning processes affecting project success," Int. J. Qual. Res., vol. 11, pp. 159-172, 2017, doi: 10.18421/IJQR11.01-10.
</mixed-citation>
</ref>
<ref id="R12">
<label>[12]</label>
<mixed-citation publication-type="other">A. Gill, "An effect-cause-effect analysis of project objectives and trade-off assumptions," Int. J. Manag. Proj. Bus., vol. 1, pp. 535-551, 2008, doi: 10.1108/17538370810906246.
</mixed-citation>
</ref>
<ref id="R13">
<label>[13]</label>
<mixed-citation publication-type="other">N. Burghate, "Work Breakdown Structure&#x0202f;: Simplifying Project Management," Int. J. Commer. Manag. Stud., vol. 3, no. 2, 2018.
</mixed-citation>
</ref>
<ref id="R14">
<label>[14]</label>
<mixed-citation publication-type="other">A. Yismalet and D. Patel, "A Critical Literature Review on Improving Project Cost Management Practice and Profitability of Domestic Contractors," Int. J. Eng. Technol. Manag. Res., vol. 5, no. 1, pp. 51-58, Feb. 2018, doi: 10.29121/ijetmr.v5.i1.2018.48.
</mixed-citation>
</ref>
<ref id="R15">
<label>[15]</label>
<mixed-citation publication-type="other">R. Kaur, "A Review of various Software Project Scheduling techniques," Int. J. Comput. Sci. Eng. Technol., vol. 4, no. 07, pp. 877-882, 2013.
</mixed-citation>
</ref>
<ref id="R16">
<label>[16]</label>
<mixed-citation publication-type="other">D. Trietsch and K. R. Baker, "PERT 21: Fitting PERT/CPM for use in the 21st century," Int. J. Proj. Manag., vol. 30, no. 4, pp. 490-502, May 2012, doi: 10.1016/j.ijproman.2011.09.004.
</mixed-citation>
</ref>
<ref id="R17">
<label>[17]</label>
<mixed-citation publication-type="other">S. Biswas, C. Karmaker, and T. Biswas, "Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study," Int. J. Comput. Eng. Res., 2016.
</mixed-citation>
</ref>
<ref id="R18">
<label>[18]</label>
<mixed-citation publication-type="other">A. R. Rao, "Resource Allocation In Project Scheduling Application of," Int. J. Appl. Eng. Res., vol. 10, no. 8, pp. 20403-20414, 2015.
</mixed-citation>
</ref>
<ref id="R19">
<label>[19]</label>
<mixed-citation publication-type="other">H. Province and A. Province, "Cost/Schedule Monitoring and Forecasting for Project Based on Earned Value Management (EVM) Jianwen HUANG 1," Adv. Mater. Res., vol. 921, pp. 1437-1440, 2014, doi: 10.4028/www.scientific.net/AMR.919-921.1437.
</mixed-citation>
</ref>
<ref id="R20">
<label>[20]</label>
<mixed-citation publication-type="other">M. Vanhoucke, The Data-Driven Project Manager. Berkeley, CA: Apress, 2018. doi: 10.1007/978-1-4842-3498-3.
</mixed-citation>
</ref>
<ref id="R21">
<label>[21]</label>
<mixed-citation publication-type="other">B. Stvilia et al., "Research project tasks, data, and perceptions of data quality in a condensed matter physics community," J. Assoc. Inf. Sci. Technol., vol. 66, no. 2, pp. 246-263, Feb. 2015, doi: 10.1002/asi.23177.
</mixed-citation>
</ref>
<ref id="R22">
<label>[22]</label>
<mixed-citation publication-type="other">S. A. Abdel Azeem, H. E. Hosny, and A. H. Ibrahim, "Forecasting project schedule performance using probabilistic and deterministic models," HBRC J., vol. 10, no. 1, pp. 35-42, Apr. 2014, doi: 10.1016/j.hbrcj.2013.09.002.
</mixed-citation>
</ref>
<ref id="R23">
<label>[23]</label>
<mixed-citation publication-type="other">T. Wauters, K. Verbeeck, G. Vanden Berghe, and P. De Causmaecker, "Learning agents for the multi-mode project scheduling problem," J. Oper. Res. Soc., vol. 62, no. 2, pp. 281-290, Feb. 2011, doi: 10.1057/jors.2010.101.
</mixed-citation>
</ref>
<ref id="R24">
<label>[24]</label>
<mixed-citation publication-type="other">P. I. Adamu and O. T. Aromolaran, "Machine Learning Priority Rule ( MLPR ) For Solving Resource-Constrained Project Scheduling Problems," Proc. Int. MultiConference Eng. Comput. Sci., vol. II, 2018.
</mixed-citation>
</ref>
<ref id="R25">
<label>[25]</label>
<mixed-citation publication-type="other">R. Sathya and A. Abraham, "Comparison of Supervised and Unsupervised Learning Algorithms for Pattern Classification," Int. J. Adv. Res. Artif. Intell., vol. 2, no. 2, 2013, doi: 10.14569/IJARAI.2013.020206.
</mixed-citation>
</ref>
<ref id="R26">
<label>[26]</label>
<mixed-citation publication-type="other">M. Usama et al., "Unsupervised Machine Learning for Networking: Techniques, Applications and Research Challenges," IEEE Access, vol. 7, pp. 65579-65615, 2019, doi: 10.1109/ACCESS.2019.2916648.
</mixed-citation>
</ref>
<ref id="R27">
<label>[27]</label>
<mixed-citation publication-type="other">T. Wauters, K. Verbeeck, P. De Causmaecker, and G. Vanden Berghe, "A learning-based optimization approach to multi-project scheduling," J. Sched., vol. 18, 2015, doi: 10.1007/s10951-014-0401-1.
</mixed-citation>
</ref>
<ref id="R28">
<label>[28]</label>
<mixed-citation publication-type="other">W. Wang, X. Ge, L. Li, and J. Su, "Proactive and Reactive Multi-Project Scheduling in Uncertain Environment," IEEE Access, vol. 7, pp. 88986-88997, 2019, doi: 10.1109/ACCESS.2019.2926337.
</mixed-citation>
</ref>
<ref id="R29">
<label>[29]</label>
<mixed-citation publication-type="other">A. Shimoda, P. Wilairath, and T. Kounosu, "Project Planning from the Viewpoint of Project Management and Systems Engineering," in 2019 IEEE International Conference on Engineering, Technology and Education (TALE), 2019, pp. 1-8. doi: 10.1109/TALE48000.2019.9226007.
</mixed-citation>
</ref>
<ref id="R30">
<label>[30]</label>
<mixed-citation publication-type="other">O. Zachko and D. Kobylkin, "Discrete-Event Modeling of the Critical Parameters of Functioning the Products of Infrastructure Projects at the Planning Stage," in 2018 IEEE 13th International Scientific and Technical Conference on Computer Sciences and Information Technologies (CSIT), 2018, pp. 152-155. doi: 10.1109/STC-CSIT.2018.8526629.
</mixed-citation>
</ref>
<ref id="R31">
<label>[31]</label>
<mixed-citation publication-type="other">W. Kusturica, C. Laroque, D. Gliem, J. Stolipin, and S. Wenzel, "Estimating Process Duration and Safeguard Project Planning in A One-of-A-Kind Production Environment by the Use of Simulation," in 2018 Winter Simulation Conference (WSC), IEEE, Dec. 2018, pp. 3909-3920. doi: 10.1109/WSC.2018.8632299.
</mixed-citation>
</ref>
<ref id="R32">
<label>[32]</label>
<mixed-citation publication-type="other">M. Hameed, H. Khalid, U. Qamar, and S. K. Abass, "Optimizing software project management staffing and work-force deployment processes using swarm intelligence," in 2017 Computing Conference, 2017, pp. 78-84. doi: 10.1109/SAI.2017.8252084.
</mixed-citation>
</ref>
<ref id="R33">
<label>[33]</label>
<mixed-citation publication-type="other">T. Rihm and N. Trautmann, "An assignment-based continuous-time MILP model for the resource-constrained project scheduling problem," in 2017 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM), 2017, pp. 35-39. doi: 10.1109/IEEM.2017.8289846.
</mixed-citation>
</ref>
<ref id="R34">
<label>[34]</label>
<mixed-citation publication-type="other">A. Peralta, E. Conde, M. Garc&#x000ed;a, and F. P. Romero, "Behavioral Pattern Recognition and Knowledge Extraction for Decision-Making in Software Project Management," in 2016 International Conference on Computational Science and Computational Intelligence (CSCI), 2016, pp. 865-868. doi: 10.1109/CSCI.2016.0168.
</mixed-citation>
</ref>
<ref id="R1">
<label>[1]</label>
<mixed-citation publication-type="other">J. L. Leal, J. P. Rodr&#x000ed;guez, and O. A. Gallardo, "Project time: Time management method for software development projects-analytical summary," J. Phys. Conf. Ser., vol. 1126, Nov. 2018, doi: 10.1088/1742-6596/1126/1/012030.
</mixed-citation>
</ref>
<ref id="R2">
<label>[2]</label>
<mixed-citation publication-type="other">R. G. Sol&#x000ed;s-Carca&#x000f1;o, G. A. Corona-Su&#x000e1;rez, and A. J. Garc&#x000ed;a-Ibarra, "The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico," J. Constr. Eng., pp. 1-9, Oct. 2015, doi: 10.1155/2015/868479.
</mixed-citation>
</ref>
<ref id="R3">
<label>[3]</label>
<mixed-citation publication-type="other">P. L. Sharma, S. Gupta, and N. Dhiman, "Construction of Maximum Distance Separable Rhotrices using Cauchy Rhotrices over Finite Fields," Int. J. Comput. Appl., vol. 168, no. 9, pp. 8-17, Jun. 2017, doi: 10.5120/ijca2017914489.
</mixed-citation>
</ref>
<ref id="R4">
<label>[4]</label>
<mixed-citation publication-type="other">J. Sharanyasreenivas, G. Gajalakshmi, and K. R. Theja, "Project Planning, Scheduling and Preparation of Quality Assurance Control Documents," Int. Res. J. Eng. Technol., vol. 4, no. 11, pp. 1862-1869, 2017.
</mixed-citation>
</ref>
<ref id="R5">
<label>[5]</label>
<mixed-citation publication-type="other">P. M. Wale, N. D. Jain, N. R. Godhani, S. R. Beniwal, and A. A. Mir, "Planning and Scheduling of Project using Microsoft Project ( Case Study of a building in India )," IOSR J. Mech. Civ. Eng., vol. 12, no. 3, pp. 57-63, 2015.
</mixed-citation>
</ref>
<ref id="R6">
<label>[6]</label>
<mixed-citation publication-type="other">R. Pellerin and N. Perrier, "A review of methods, techniques and tools for project planning and control," Int. J. Prod. Res., vol. 57, no. 7, pp. 2160-2178, Apr. 2019, doi: 10.1080/00207543.2018.1524168.
</mixed-citation>
</ref>
<ref id="R7">
<label>[7]</label>
<mixed-citation publication-type="other">P. V&#x000e4;h&#x000e4;kainu and M. Lehto, "Artificial intelligence in the cyber security environment Artificial intelligence in the cyber security environment," in The 14th International Conference on Cyber Warfare and Security ICCWS2019, 2019, pp. 431-440.
</mixed-citation>
</ref>
<ref id="R8">
<label>[8]</label>
<mixed-citation publication-type="other">S. Garg, "AI/ML Driven Proactive Performance Monitoring, Resource Allocation and Effective Cost Management in SAAS Operations," Int. J. Core Eng. Manag., vol. 6, no. 6, pp. 263-273, 2019.
</mixed-citation>
</ref>
<ref id="R9">
<label>[9]</label>
<mixed-citation publication-type="other">H. K. Dam, T. Tran, J. Grundy, A. Ghose, and Y. Kamei, "Towards Effective AI-Powered Agile Project Management," in 2019 IEEE/ACM 41st International Conference on Software Engineering: New Ideas and Emerging Results (ICSE-NIER), IEEE, May 2019, pp. 41-44. doi: 10.1109/ICSE-NIER.2019.00019.
</mixed-citation>
</ref>
<ref id="R10">
<label>[10]</label>
<mixed-citation publication-type="other">S. Atin and R. Lubis, "Implementation of Critical Path Method in Project Planning and Scheduling," IOP Conf. Ser. Mater. Sci. Eng., vol. 662, p. 22031, 2019, doi: 10.1088/1757-899X/662/2/022031.
</mixed-citation>
</ref>
<ref id="R11">
<label>[11]</label>
<mixed-citation publication-type="other">T. Woldassilasie, E. Berhan, and B. Beshah, "Key project planning processes affecting project success," Int. J. Qual. Res., vol. 11, pp. 159-172, 2017, doi: 10.18421/IJQR11.01-10.
</mixed-citation>
</ref>
<ref id="R12">
<label>[12]</label>
<mixed-citation publication-type="other">A. Gill, "An effect-cause-effect analysis of project objectives and trade-off assumptions," Int. J. Manag. Proj. Bus., vol. 1, pp. 535-551, 2008, doi: 10.1108/17538370810906246.
</mixed-citation>
</ref>
<ref id="R13">
<label>[13]</label>
<mixed-citation publication-type="other">N. Burghate, "Work Breakdown Structure&#x0202f;: Simplifying Project Management," Int. J. Commer. Manag. Stud., vol. 3, no. 2, 2018.
</mixed-citation>
</ref>
<ref id="R14">
<label>[14]</label>
<mixed-citation publication-type="other">A. Yismalet and D. Patel, "A Critical Literature Review on Improving Project Cost Management Practice and Profitability of Domestic Contractors," Int. J. Eng. Technol. Manag. Res., vol. 5, no. 1, pp. 51-58, Feb. 2018, doi: 10.29121/ijetmr.v5.i1.2018.48.
</mixed-citation>
</ref>
<ref id="R15">
<label>[15]</label>
<mixed-citation publication-type="other">R. Kaur, "A Review of various Software Project Scheduling techniques," Int. J. Comput. Sci. Eng. Technol., vol. 4, no. 07, pp. 877-882, 2013.
</mixed-citation>
</ref>
<ref id="R16">
<label>[16]</label>
<mixed-citation publication-type="other">D. Trietsch and K. R. Baker, "PERT 21: Fitting PERT/CPM for use in the 21st century," Int. J. Proj. Manag., vol. 30, no. 4, pp. 490-502, May 2012, doi: 10.1016/j.ijproman.2011.09.004.
</mixed-citation>
</ref>
<ref id="R17">
<label>[17]</label>
<mixed-citation publication-type="other">S. Biswas, C. Karmaker, and T. Biswas, "Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study," Int. J. Comput. Eng. Res., 2016.
</mixed-citation>
</ref>
<ref id="R18">
<label>[18]</label>
<mixed-citation publication-type="other">A. R. Rao, "Resource Allocation In Project Scheduling Application of," Int. J. Appl. Eng. Res., vol. 10, no. 8, pp. 20403-20414, 2015.
</mixed-citation>
</ref>
<ref id="R19">
<label>[19]</label>
<mixed-citation publication-type="other">H. Province and A. Province, "Cost/Schedule Monitoring and Forecasting for Project Based on Earned Value Management (EVM) Jianwen HUANG 1," Adv. Mater. Res., vol. 921, pp. 1437-1440, 2014, doi: 10.4028/www.scientific.net/AMR.919-921.1437.
</mixed-citation>
</ref>
<ref id="R20">
<label>[20]</label>
<mixed-citation publication-type="other">M. Vanhoucke, The Data-Driven Project Manager. Berkeley, CA: Apress, 2018. doi: 10.1007/978-1-4842-3498-3.
</mixed-citation>
</ref>
<ref id="R21">
<label>[21]</label>
<mixed-citation publication-type="other">B. Stvilia et al., "Research project tasks, data, and perceptions of data quality in a condensed matter physics community," J. Assoc. Inf. Sci. Technol., vol. 66, no. 2, pp. 246-263, Feb. 2015, doi: 10.1002/asi.23177.
</mixed-citation>
</ref>
<ref id="R22">
<label>[22]</label>
<mixed-citation publication-type="other">S. A. Abdel Azeem, H. E. Hosny, and A. H. Ibrahim, "Forecasting project schedule performance using probabilistic and deterministic models," HBRC J., vol. 10, no. 1, pp. 35-42, Apr. 2014, doi: 10.1016/j.hbrcj.2013.09.002.
</mixed-citation>
</ref>
<ref id="R23">
<label>[23]</label>
<mixed-citation publication-type="other">T. Wauters, K. Verbeeck, G. Vanden Berghe, and P. De Causmaecker, "Learning agents for the multi-mode project scheduling problem," J. Oper. Res. Soc., vol. 62, no. 2, pp. 281-290, Feb. 2011, doi: 10.1057/jors.2010.101.
</mixed-citation>
</ref>
<ref id="R24">
<label>[24]</label>
<mixed-citation publication-type="other">P. I. Adamu and O. T. Aromolaran, "Machine Learning Priority Rule ( MLPR ) For Solving Resource-Constrained Project Scheduling Problems," Proc. Int. MultiConference Eng. Comput. Sci., vol. II, 2018.
</mixed-citation>
</ref>
<ref id="R25">
<label>[25]</label>
<mixed-citation publication-type="other">R. Sathya and A. Abraham, "Comparison of Supervised and Unsupervised Learning Algorithms for Pattern Classification," Int. J. Adv. Res. Artif. Intell., vol. 2, no. 2, 2013, doi: 10.14569/IJARAI.2013.020206.
</mixed-citation>
</ref>
<ref id="R26">
<label>[26]</label>
<mixed-citation publication-type="other">M. Usama et al., "Unsupervised Machine Learning for Networking: Techniques, Applications and Research Challenges," IEEE Access, vol. 7, pp. 65579-65615, 2019, doi: 10.1109/ACCESS.2019.2916648.
</mixed-citation>
</ref>
<ref id="R27">
<label>[27]</label>
<mixed-citation publication-type="other">T. Wauters, K. Verbeeck, P. De Causmaecker, and G. Vanden Berghe, "A learning-based optimization approach to multi-project scheduling," J. Sched., vol. 18, 2015, doi: 10.1007/s10951-014-0401-1.
</mixed-citation>
</ref>
<ref id="R28">
<label>[28]</label>
<mixed-citation publication-type="other">W. Wang, X. Ge, L. Li, and J. Su, "Proactive and Reactive Multi-Project Scheduling in Uncertain Environment," IEEE Access, vol. 7, pp. 88986-88997, 2019, doi: 10.1109/ACCESS.2019.2926337.
</mixed-citation>
</ref>
<ref id="R29">
<label>[29]</label>
<mixed-citation publication-type="other">A. Shimoda, P. Wilairath, and T. Kounosu, "Project Planning from the Viewpoint of Project Management and Systems Engineering," in 2019 IEEE International Conference on Engineering, Technology and Education (TALE), 2019, pp. 1-8. doi: 10.1109/TALE48000.2019.9226007.
</mixed-citation>
</ref>
<ref id="R30">
<label>[30]</label>
<mixed-citation publication-type="other">O. Zachko and D. Kobylkin, "Discrete-Event Modeling of the Critical Parameters of Functioning the Products of Infrastructure Projects at the Planning Stage," in 2018 IEEE 13th International Scientific and Technical Conference on Computer Sciences and Information Technologies (CSIT), 2018, pp. 152-155. doi: 10.1109/STC-CSIT.2018.8526629.
</mixed-citation>
</ref>
<ref id="R31">
<label>[31]</label>
<mixed-citation publication-type="other">W. Kusturica, C. Laroque, D. Gliem, J. Stolipin, and S. Wenzel, "Estimating Process Duration and Safeguard Project Planning in A One-of-A-Kind Production Environment by the Use of Simulation," in 2018 Winter Simulation Conference (WSC), IEEE, Dec. 2018, pp. 3909-3920. doi: 10.1109/WSC.2018.8632299.
</mixed-citation>
</ref>
<ref id="R32">
<label>[32]</label>
<mixed-citation publication-type="other">M. Hameed, H. Khalid, U. Qamar, and S. K. Abass, "Optimizing software project management staffing and work-force deployment processes using swarm intelligence," in 2017 Computing Conference, 2017, pp. 78-84. doi: 10.1109/SAI.2017.8252084.
</mixed-citation>
</ref>
<ref id="R33">
<label>[33]</label>
<mixed-citation publication-type="other">T. Rihm and N. Trautmann, "An assignment-based continuous-time MILP model for the resource-constrained project scheduling problem," in 2017 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM), 2017, pp. 35-39. doi: 10.1109/IEEM.2017.8289846.
</mixed-citation>
</ref>
<ref id="R34">
<label>[34]</label>
<mixed-citation publication-type="other">A. Peralta, E. Conde, M. Garc&#x000ed;a, and F. P. Romero, "Behavioral Pattern Recognition and Knowledge Extraction for Decision-Making in Software Project Management," in 2016 International Conference on Computational Science and Computational Intelligence (CSCI), 2016, pp. 865-868. doi: 10.1109/CSCI.2016.0168.
</mixed-citation>
</ref>
    </ref-list>
  </back>
</article>