Evaluation of the Incidences of Risk Occurrence and Severity in PPP-Procured Mass Housing Projects (PPP-MHPs) in Abuja, Nigeria

Table 4.

Level of Risk Occurrence/Probability in PPPProcured Mass Housing Projects Cont.

Risk Factors Risk Probability Std. Deviation Rank Asymp. Sig

Operational revenue below the projection 4.69 0.622 39 .000*
Inconsistencies in Government Policies 4.68 0.711 40 0.143
Environment 4.64 0.681 41 .000*
Third-party tort liability 4.57 0.657 42 .000*
Different working methods/know-how between partners 4.54 0.789 43 0.080
Change in tax regulation 4.50 0.795 44 0.852
Residual value (After the concession period) 4.47 0.764 45 .000*
Design deficiencies 4.47 0.943 46 0.548
Availability of appropriate labor/material 4.45 0.763 47 0.019
Excessive contract variation 4.43 0.715 48 .000*
Low operating productivity 4.41 0.823 49 0.025
Rate of Return restrictions 4.39 0.940 50 .000*
Lack of Government guarantee 4.39 1.001 51 0.009
Industrial regulation change 4.33 0.726 52 .005*
Legislation change/Inconsistencies 4.28 0.715 53 0.092
Cultural differences between the main Stakeholders 4.27 1.159 54 0.672
Insolvency/default of Subcontractors and Suppliers 4.25 0.655 55 .000*
Strong Political opposition 4.21 0.685 56 .000*
Unproven Engineering techniques 4.20 0.719 57 .000*
Import and Export restriction 4.19 0.645 58 .001*
Poor Quality of Workmanship 4.12 0.754 59 .000*
Possible expropriation/nationalization of assets 4.12 0.755 60 .000*
Geotechnical conditions 4.12 0.895 61 0.289
Staff crises 4.11 0.686 62 .000*
Late design changes 4.00 0.851 63 0.016