Evaluation of the Incidences of Risk Occurrence and Severity in PPP-Procured Mass Housing Projects (PPP-MHPs) in Abuja, Nigeria
Table 4.
Level of Risk Occurrence/Probability in PPPProcured Mass Housing Projects Cont.
|
| Risk Factors |
Risk Probability |
Std. Deviation |
Rank |
Asymp. Sig |
|
|
| Operational revenue below the projection |
4.69 |
0.622 |
39 |
.000* |
|
| Inconsistencies in Government Policies |
4.68 |
0.711 |
40 |
0.143 |
|
| Environment |
4.64 |
0.681 |
41 |
.000* |
|
| Third-party tort liability |
4.57 |
0.657 |
42 |
.000* |
|
| Different working methods/know-how between partners |
4.54 |
0.789 |
43 |
0.080 |
|
| Change in tax regulation |
4.50 |
0.795 |
44 |
0.852 |
|
| Residual value (After the concession period) |
4.47 |
0.764 |
45 |
.000* |
|
| Design deficiencies |
4.47 |
0.943 |
46 |
0.548 |
|
| Availability of appropriate labor/material |
4.45 |
0.763 |
47 |
0.019 |
|
| Excessive contract variation |
4.43 |
0.715 |
48 |
.000* |
|
| Low operating productivity |
4.41 |
0.823 |
49 |
0.025 |
|
| Rate of Return restrictions |
4.39 |
0.940 |
50 |
.000* |
|
| Lack of Government guarantee |
4.39 |
1.001 |
51 |
0.009 |
|
| Industrial regulation change |
4.33 |
0.726 |
52 |
.005* |
|
| Legislation change/Inconsistencies |
4.28 |
0.715 |
53 |
0.092 |
|
| Cultural differences between the main Stakeholders |
4.27 |
1.159 |
54 |
0.672 |
|
| Insolvency/default of Subcontractors and Suppliers |
4.25 |
0.655 |
55 |
.000* |
|
| Strong Political opposition |
4.21 |
0.685 |
56 |
.000* |
|
| Unproven Engineering techniques |
4.20 |
0.719 |
57 |
.000* |
|
| Import and Export restriction |
4.19 |
0.645 |
58 |
.001* |
|
| Poor Quality of Workmanship |
4.12 |
0.754 |
59 |
.000* |
|
| Possible expropriation/nationalization of assets |
4.12 |
0.755 |
60 |
.000* |
|
| Geotechnical conditions |
4.12 |
0.895 |
61 |
0.289 |
|
| Staff crises |
4.11 |
0.686 |
62 |
.000* |
|
| Late design changes |
4.00 |
0.851 |
63 |
0.016 |
|
|
|
|