| Risk Factors |
Risk Probability |
Std. Deviation |
Risk Severity |
Std. Deviation |
Risk impact |
Normalized Value |
Rank |
Risk Criticality |
|
|
| Availability of Finance |
6.60 |
0.855 |
6.54 |
0.544 |
6.57 |
1.00 |
1 |
Extremely High |
|
| High Finance cost |
6.27 |
0.740 |
6.22 |
0.540 |
6.25 |
0.87 |
2 |
Very High |
|
| Corruption and lack of respect for Law |
6.06 |
0.446 |
6.03 |
0.408 |
6.04 |
0.78 |
3 |
Very High |
|
| Non-involvement of the host community |
6.06 |
0.544 |
5.90 |
0.567 |
5.98 |
0.76 |
4 |
Very High |
|
| Poor execution of Housing Policies |
6.06 |
0.471 |
5.88 |
0.516 |
5.97 |
0.75 |
5 |
Very High |
|
| Wrong perception of housing need by low-income earners |
5.97 |
0.462 |
5.98 |
0.305 |
5.97 |
0.75 |
6 |
Very High |
|
| Illegal Title to Land |
5.94 |
0.418 |
5.90 |
0.397 |
5.92 |
0.73 |
7 |
Very High |
|
| Land acquisition and Site availability |
5.91 |
1.155 |
5.92 |
0.488 |
5.91 |
0.73 |
8 |
Very High |
|
| Level of Demand for the mass housing projects |
5.82 |
0.808 |
5.83 |
0.458 |
5.83 |
0.69 |
9 |
Very High |
|
| Inadequate experience in PPP |
5.75 |
0.749 |
5.79 |
0.512 |
5.77 |
0.67 |
10 |
Very High |
|
| Unstable Value of Local Currency |
5.78 |
0.471 |
5.68 |
0.566 |
5.73 |
0.65 |
11 |
Very High |
|
| Lack of creditworthiness |
5.67 |
0.787 |
5.68 |
0.690 |
5.67 |
0.63 |
12 |
Very High |
|
| Inadequate distribution of responsibility and risks |
5.53 |
0.987 |
5.76 |
0.644 |
5.64 |
0.62 |
13 |
Very High |
|
| Risk regarding Pricing of Product/service |
5.62 |
0.639 |
5.57 |
0.682 |
5.59 |
0.60 |
14 |
Very High |
|
| Lack of Commitment from Public/Private Partners |
5.47 |
0.717 |
5.60 |
0.623 |
5.53 |
0.57 |
15 |
Very High |
|
| Prolonged negotiation period prior to initiation |
5.55 |
0.758 |
5.48 |
0.586 |
5.52 |
0.56 |
16 |
Very High |
|
| Construction time delay |
5.39 |
0.658 |
5.62 |
0.511 |
5.50 |
0.56 |
17 |
Very High |
|
| Influential Economic Events (Boom/Recession) |
5.55 |
0.916 |
5.41 |
0.785 |
5.48 |
0.55 |
18 |
High |
|
| High Bidding cost |
5.52 |
0.765 |
5.38 |
0.848 |
5.45 |
0.54 |
19 |
High |
|
| Poor Financial Market |
5.43 |
0.792 |
5.46 |
0.963 |
5.45 |
0.54 |
20 |
High |
|
| Inadequate distribution of Authority between Partners |
5.34 |
0.695 |
5.51 |
0.765 |
5.43 |
0.53 |
21 |
High |
|
| Poor decision-making process |
5.38 |
0.800 |
5.45 |
0.604 |
5.41 |
0.52 |
22 |
High |
|
| Financial attraction to project investors |
5.40 |
0.942 |
5.36 |
1.047 |
5.38 |
0.51 |
23 |
High |
|
| Construction cost overrun |
5.26 |
0.602 |
5.50 |
0.567 |
5.38 |
0.51 |
24 |
High |
|
| Force majeure |
5.17 |
0.957 |
5.54 |
1.033 |
5.36 |
0.50 |
25 |
High |
|
| Delay in Project approvals and permits |
5.34 |
0.768 |
5.34 |
0.641 |
5.34 |
0.50 |
26 |
High |
|
| Interest rate volatility |
5.19 |
0.824 |
5.47 |
0.760 |
5.33 |
0.50 |
27 |
High |
|
| Change in Government |
5.24 |
0.788 |
5.30 |
1.073 |
5.27 |
0.50 |
28 |
High |
|
| Inflation rate volatility |
5.39 |
0.802 |
5.06 |
0.992 |
5.22 |
0.50 |
29 |
High |
|
| Land Grabbing/Encroachment |
4.95 |
0.852 |
5.52 |
0.770 |
5.22 |
0.50 |
30 |
High |
|
| Public opposition to the mass housing projects |
5.22 |
1.088 |
5.15 |
1.286 |
5.19 |
0.50 |
31 |
High |
|
| Weather |
5.11 |
0.871 |
5.08 |
1.092 |
5.09 |
0.39 |
32 |
High |
|
| Operation cost overrun |
5.05 |
0.658 |
5.04 |
0.716 |
5.05 |
0.37 |
33 |
High |
|
| Organization and Coordination risk |
4.90 |
0.975 |
4.92 |
0.805 |
4.91 |
0.31 |
34 |
High |
|
| Inability to service debt |
4.81 |
0.813 |
4.99 |
0.895 |
4.90 |
0.31 |
35 |
High |
|
| The bankruptcy of the investors (OPS) |
4.72 |
0.883 |
4.87 |
1.028 |
4.79 |
0.27 |
36 |
High |
|
| Operational revenue below the projection |
4.69 |
0.622 |
4.80 |
0.719 |
4.74 |
0.25 |
37 |
High |
|
| Lack of tradition of private provision of public services |
4.74 |
1.157 |
4.70 |
0.999 |
4.72 |
0.23 |
38 |
High |
|
| Inconsistencies in Government Policies |
4.68 |
0.711 |
4.66 |
1.105 |
4.67 |
0.22 |
39 |
High |
|
| Excessive contract variation |
4.43 |
0.715 |
4.93 |
0.832 |
4.68 |
0.22 |
40 |
High |
|
| Competition risk |
4.74 |
0.618 |
4.55 |
0.837 |
4.64 |
0.20 |
41 |
High |
|
| Different working methods/know-how between partners |
4.54 |
0.789 |
4.75 |
0.781 |
4.64 |
0.20 |
42 |
High |
|
| Environment |
4.64 |
0.681 |
4.67 |
0.639 |
4.66 |
0.21 |
43 |
High |
|
| Insolvency/default of Subcontractors and Suppliers |
4.25 |
0.655 |
5.02 |
0.873 |
4.62 |
0.19 |
44 |
High |
|
| Third party tort liability |
4.57 |
0.657 |
4.61 |
0.692 |
4.59 |
0.18 |
45 |
High |
|
| Availability of appropriate labour/material |
4.45 |
0.763 |
4.64 |
0.912 |
4.54 |
0.16 |
46 |
High |
|
| Lack of Government guarantee |
4.39 |
1.001 |
4.70 |
1.091 |
4.54 |
0.16 |
47 |
High |
|
| Low operating productivity |
4.41 |
0.823 |
4.59 |
0.619 |
4.50 |
0.14 |
48 |
High |
|
| Rate of Return restrictions |
4.39 |
0.940 |
4.60 |
1.177 |
4.49 |
0.14 |
49 |
Moderate |
|
| Legislation change/Inconsistencies |
4.28 |
0.715 |
4.68 |
0.861 |
4.47 |
0.13 |
50 |
Moderate |
|
| Design deficiencies |
4.47 |
0.943 |
4.40 |
1.150 |
4.43 |
0.12 |
51 |
Moderate |
|
| Geotechnical conditions |
4.12 |
0.895 |
4.79 |
0.946 |
4.45 |
0.12 |
52 |
Moderate |
|
| Residual value (After concession period) |
4.47 |
0.764 |
4.38 |
0.771 |
4.42 |
0.11 |
53 |
Moderate |
|
| Change in tax regulation |
4.50 |
0.795 |
4.29 |
1.016 |
4.40 |
0.10 |
54 |
Moderate |
|
| Import and Export restriction |
4.19 |
0.645 |
4.49 |
0.625 |
4.33 |
0.08 |
55 |
Moderate |
|
| Possible expropriation/nationalization of assets |
4.12 |
0.755 |
4.60 |
0.912 |
4.35 |
0.08 |
56 |
Moderate |
|
| Industrial regulation change |
4.33 |
0.726 |
4.30 |
0.755 |
4.32 |
0.07 |
57 |
Moderate |
|
| Unproven Engineering techniques |
4.20 |
0.719 |
4.45 |
0.694 |
4.32 |
0.07 |
58 |
Moderate |
|
| Poor Quality of Workmanship |
4.12 |
0.754 |
4.48 |
0.814 |
4.30 |
0.06 |
59 |
Moderate |
|
| Cultural differences between the main Stakeholders |
4.27 |
1.159 |
4.23 |
1.189 |
4.25 |
0.04 |
60 |
Moderate |
|
| Staff crises |
4.11 |
0.686 |
4.36 |
0.589 |
4.23 |
0.03 |
61 |
Moderate |
|
| Strong Political opposition |
4.21 |
0.685 |
4.14 |
0.913 |
4.17 |
0.01 |
62 |
Moderate |
|
| Late design changes |
4.00 |
0.851 |
4.30 |
1.041 |
4.15 |
0.00 |
63 |
Moderate |
|
|