| Critical Risk Factors and Category |
Risk impact |
Overall Ranking |
Ranking within category |
|
|
| Financial and Macroeconomic risk (CRFG 1): u1 |
|
|
|
|
| Availability of Finance, u11 |
6.57 |
1 |
1 |
|
| High Finance cost, u12 |
6.25 |
2 |
2 |
|
| Unstable Value of Local Currency, u13 |
5.73 |
11 |
3 |
|
| Lack of creditworthiness, u14 |
5.67 |
12 |
4 |
|
| Influential Economic Events (Boom/Recession), u15 |
5.48 |
18 |
5 |
|
| High Bidding cost, u16 |
5.45 |
19 |
6 |
|
| Poor Financial Market, u17 |
5.45 |
20 |
7 |
|
| Financial attraction to project investors, u18 |
5.38 |
23 |
8 |
|
| Interest rate volatility, u19 |
5.33 |
27 |
9 |
|
| Inflation rate volatility, u110 |
5.22 |
29 |
10 |
|
| Legal and Socio-political risk (CRFG 2): u2 |
|
|
|
|
| Corruption and lack of respect for Law, u21 |
6.04 |
3 |
1 |
|
| Non-involvement of the host community, u22 |
5.98 |
4 |
2 |
|
| Poor execution of Housing Policies, u23 |
5.97 |
5 |
3 |
|
| Wrong perception of housing need by low-income earners, u24 |
5.97 |
6 |
4 |
|
| Illegal Title to Land, u25 |
5.92 |
7 |
5 |
|
| Poor decision-making process, u26 |
5.41 |
22 |
6 |
|
| Change in Government, u27 |
5.27 |
28 |
7 |
|
| Land Grabbing/Encroachment, u28 |
5.22 |
30 |
8 |
|
| Public opposition to the mass housing projects, u29 |
5.19 |
31 |
9 |
|
| Operation and Organization risk (CRFG 3): u3 |
|
|
|
|
| Inadequate experience in PPP, u31 |
5.77 |
10 |
1 |
|
| Inadequate distribution of responsibility and risks, u32 |
5.64 |
13 |
2 |
|
| Risk regarding Pricing of Product/service, u33 |
5.59 |
14 |
3 |
|
| Lack of Commitment from Public/Private Partners, u34 |
5.53 |
15 |
4 |
|
| Inadequate distribution of Authority between Partners, u35 |
5.43 |
21 |
5 |
|
| Design and Project Selection risk (CRFG 4): u4 |
|
|
|
|
| Land acquisition and Site availability, u41 |
5.91 |
8 |
1 |
|
| Level of Demand for the mass housing projects, u42 |
5.83 |
9 |
2 |
|
| Prolonged negotiation period before initiation, u43 |
5.52 |
16 |
3 |
|
| Delay in Project approvals and permits, u44 |
5.34 |
26 |
4 |
|
| Construction risk (CRFG 5): u5 |
|
|
|
|
| Construction time delay, u51 |
5.50 |
17 |
1 |
|
| Construction cost overrun, u52 |
5.38 |
24 |
2 |
|
| Force Majeure, u53 |
5.36 |
25 |
3 |
|
|