| CRFs and PRFs |
Weighting (wn) for CRFs |
Membership function for level 3 CRFs |
Membership function for level 2 CRFG |
|
|
| Financial and Macroeconomic risk (CRFG 1): u1 |
|
|
(0.00,0.00,0.02,0.08,0.21,0.56,0.12) |
|
| Availability of Finance, u11 |
0.116 |
(0.00,0.00,0.00,0.00,0.02,0.41,0.57) |
|
|
| High Finance cost, u12 |
0.111 |
(0.00,0.00,0.00,0.00,0.06,0.66,0.28) |
|
|
| Unstable Value of Local Currency, u13 |
0.101 |
(0.00,0.00,0.00,0.05,0.22,0.73,0.00) |
|
|
| Lack of credit worthiness, u14 |
0.101 |
(0.00,0.00,0.03,0.01,0.21,0.74,0.01) |
|
|
| Influential Economic Events (Boom/Recession), u15 |
0.096 |
(0.00,0.00,0.00,0.16,0.29,0.53,0.02) |
|
|
| High Bidding cost, u16 |
0.096 |
(0.00,0.00,0.02,0.14,0.31,0.50,0.03) |
|
|
| Poor Financial Market, u17 |
0.097 |
(0.00,0.00,0.07,0.08,0.19,0.62,0.04) |
|
|
| Financial attraction to project investors, u18 |
0.095 |
(0.00,0.00,0.12,0.00,0.32,0.50,0.06) |
|
|
| Interest rate volatility, u19 |
0.097 |
(0.00,0.00,0.01,0.13,0.24,0.62,0.00) |
|
|
| Inflation rate volatility, u110 |
0.090 |
(0.00,0.02,0.00,0.27,0.36,0.30,0.05) |
|
|
| Legal and Socio-political risk (CRFG 2): u2 |
|
|
(0.00,0.01,0.01,0.06,0.18,0.70,0.04) |
|
| Corruption and lack of respect for Law, u21 |
0.118 |
(0.00,0.00,0.00,0.02,0.00,0.90,0.08) |
|
|
| Non-involvement of the host community, u22 |
0.116 |
(0.00,0.00,0.02,0.00,0.07,0.86,0.05) |
|
|
| Poor execution of Housing Policies, u23 |
0.115 |
(0.00,0.00,0.00,0.05,0.06,0.86,0.03) |
|
|
| Wrong perception of housing need by low-income earners, u24 |
0.117 |
(0.00,0.00,0.00,0.00,0.06,0.91,0.03) |
|
|
| Illegal Title to Land, u25 |
0.116 |
(0.00,0.00,0.00,0.01,0.10,0.87,0.02) |
|
|
| Poor decision making process, u26 |
0.107 |
(0.00,0.00,0.00,0.05,0.47,0.47,0.01) |
|
|
| Change in Government, u27 |
0.188 |
(0.00,0.01,0.10,0.05,0.31,0.48,0.05) |
|
|
| Land Grabbing/Encroachment, u28 |
0.108 |
(0.00,0.00,0.00,0.15,0.21,0.62,0.02) |
|
|
| Public opposition to the mass housing projects, u29 |
0.101 |
(0.00,0.04,0.09,0.20,0.11,0.49,0.07) |
|
|
| Operation and Organization risk (CRFG 3): u3 |
|
|
(0.00,0.00,0.01,0.06,0.21,0.71,0.01) |
|
| Inadequate experience in PPP, u31 |
0.205 |
(0.00,0.00,0.00,0.05,0.12,0.83,0.00) |
|
|
| Inadequate distribution of responsibility and risks, u32 |
0.204 |
(0.00,0.00,0.01,0.06,0.11,0.80,0.02) |
|
|
| Risk regarding Pricing of Product/service, u33 |
0.197 |
(0.00,0.00,0.01,0.08,0.25,0.66,0.00) |
|
|
| Lack of Commitment from Public/Private Partners, u34 |
0.199 |
(0.00,0.00,0.00,0.06,0.28,0.64,0.02) |
|
|
| Inadequate distribution of Authority between Partners, u35 |
0.195 |
(0.00,0.01,0.01,0.06,0.29,0.63,0.00) |
|
|
| Design and Project Selection risk (CRFG 4): u4 |
|
|
(0.00,0.00,0.01,0.03,0.27,0.68,0.01) |
|
| Land acquisition and Site availability, u41 |
0.262 |
(0.00,0.00,0.02,0.00,0.03,0.94,0.01) |
|
|
| Level of Demand for the mass housing projects, u42 |
0.258 |
(0.00,0.00,0.00,0.01,0.17,0.80,0.02) |
|
|
| Prolonged negotiation period prior to initiation, u43 |
0.243 |
(0.00,0.00,0.00,0.05,0.42,0.53,0.00) |
|
|
| Delay in Project approvals and permits, u44 |
0.236 |
(0.00,0.00,0.01,0.06,0.51,0.42,0.00) |
|
|
| Construction risk (CRFG 5): u5 |
|
|
(0.01,0.00,0.00,0.06,0.31,0.61,0.02) |
|
| Construction time delay, u51 |
0.337 |
(0.00,0.00,0.00,0.01,0.36,0.63,0.00) |
|
|
| Construction cost overrun, u52 |
0.330 |
(0.00,0.00,0.00,0.04,0.43,0.53,0.00) |
|
|
| Force majeure, u53 |
0.333 |
(0.02,0.00,0.00,0.13,0.13,0.67,0.05) |
|
|
|
|