Evaluation of the Critical risk factors in PPP - procured Mass Housing Projects in Abuja Nigeria - A fuzzy synthetic evaluation (FSE) approach
Table 8.
Risk indices and Ranking of CRFG in PPP-procured Mass Housing Projects
|
| Index |
Linguistic |
Index |
Linguistic |
Index |
Linguistic |
|
|
| Financial and Macroeconomic risk (CRFG 1): u1 |
5.76 |
Very High |
5.63 |
Very High |
5.69 |
Very High |
1 |
|
| Legal and Socio-political risk (CRFG 2): u2 |
5.28 |
High |
5.67 |
Very High |
5.47 |
High |
4 |
|
| Operation and Organization risk (CFRG 3): u3 |
5.56 |
High |
5.65 |
Very High |
5.60 |
Very High |
3 |
|
| Design and Project Selection risk (CRFG 4): u4 |
5.69 |
Very High |
5.65 |
Very High |
5.67 |
Very High |
2 |
|
| Construction risk (CRFG 5): u5 |
5.27 |
High |
5.60 |
Very High |
5.43 |
High |
5 |
|
| Overall risk level (ORL) of PPP mass housing |
5.70 |
Very High |
5.60 |
Very High |
5.65 |
Very High |
|
|
|
|
|