Risk FactorsRisk ProbabilityStd. DeviationRankAsymp. Sig
Availability of Finance6.600.85510.136
High Finance cost6.270.7402.000*
Non-involvement of the host community6.060.5443.000*
Poor execution of Housing Policies6.060.47140.050
Corruption and lack of respect for Law6.060.44650.016
Wrong perception of housing need by low-income earners5.970.46260.000*
Illegal Title to Land5.940.41870.018
Land acquisition and Site availability5.911.15580.286
Level of Demand for the mass housing projects5.820.80890.145
Unstable Value of Local Currency5.780.471100.874
Inadequate experience in PPP5.750.74911.000*
Lack of creditworthiness5.670.787120.200
Risk regarding Pricing of Product/service5.620.63913.000*
Prolonged negotiation period before initiation5.550.758140.015
Influential Economic Events (Boom/Recession)5.550.916150.241
Inadequate distribution of responsibility and risks5.530.98716.000*
High Bidding cost5.520.76517.003*
Lack of Commitment from Public/Private Partners5.470.717180.008*
Poor Financial Market5.430.792190.163
Financial attraction to project investors5.400.942200.163
Construction time delay5.390.658210.151
Inflation rate volatility5.390.80222.000*
Poor decision-making process5.380.800230.032
Inadequate distribution of Authority between Partners5.340.695240.205
Delays in Project approvals and permits5.340.768250.001*
Construction cost overrun5.260.602260.111
Change in Government5.240.788270.349
Public opposition to the mass housing projects5.221.088280.149
Interest rate volatility5.190.82429.000*
Force Majeure5.170.957300.043
Weather5.110.87131.000*
Operation cost overrun5.050.65832.000*
Land Grabbing/Encroachment4.950.85233.000*
Organization and Coordination risk4.900.97534.000*
Inability to service debt4.810.813350.025
Competition risk4.740.618360.124
Lack of tradition of private provision of public services4.741.157370.055
The bankruptcy of the investors (OPS)4.720.88338.000*