Evaluation of the Incidences of Risk Occurrence and Severity in PPP-Procured Mass Housing Projects (PPP-MHPs) in Abuja, Nigeria

World Journal of Civil Engineering and Architecture | Vol 2, Issue 1

Table 5. 01Table 5. Level of Severity of Risk Factors in PPPprocured Mass Housing Projects

Risk FactorsRisk SeverityStd. DeviationRankAsymp.Sig
Availability of Finance6.540.54410.593
High Finance cost6.220.542.000*
Corruption and lack of respect for Law6.030.4083.000*
Wrong perception of housing need by low-income earners5.980.30540.053
Land acquisition and Site availability5.920.48850.001*
Illegal Title to Land5.900.39760.026
Non-involvement of the host community5.900.56770.001*
Poor execution of Housing Policies5.880.5168.000*
Level of Demand for the mass housing projects5.830.45890.317
Inadequate experience in PPP5.790.51210.000*
Inadequate distribution of responsibility and risks5.760.64411.000*
Unstable Value of Local Currency5.680.56612.000*
Lack of creditworthiness5.680.69130.880
Construction time delay5.620.511140.001*
Lack of Commitment from Public/Private Partners5.600.62315.000*
Risk regarding Pricing of Product/service5.570.68216.000*
Force Majeure5.541.03317.000*