Evaluation of the Critical risk factors in PPP - procured Mass Housing Projects in Abuja Nigeria - A fuzzy synthetic evaluation (FSE) approach
World Journal of Civil Engineering and Architecture
| Vol 2, Issue 1
Table 5. Membership Function (MF) for CRFs and CRFG in PPP-procured Mass HousingProjects (Risk Occurrence)
| CRFs and CRFG | Weighting (wn) for CRFs | Membership function for level 3 CRFs | Membership function for level 2 CRFG |
| Financial and Macroeconomic risk (CRFG 1): u1 | (0.00,0.00,0.02,0.09,0.21,0.54,0.15) | ||
| Availability of Finance, u11 | 0.116 | (0.00,0.02,0.00,0.00,0.01,0.26,0.71) | |
| High Finance cost, u12 | 0.110 | (0.00,0.00,0.00,0.05,0.02,0.54,0.39) | |
| Unstable Value of Local Currency, u13 | 0.102 | (0.00,0.00,0.00,0.02,0.18,0.80,0.00) | |
| Lack of credit worthiness, u14 | 0.100 | (0.00,0.01,0.04,0.01,0.17,0.76,0.01) | |
| Influential Economic Events (Boom/Recession), u15 | 0.098 | (0.00,0.00,0.00,0.16,0.26,0.44,0.14) | |
| High Bidding cost, u16 | 0.097 | (0.00,0.00,0.04,0.05,0.29,0.61,0.01) | |
| Poor Financial Market, u17 | 0.096 | (0.00,0.00,0.04,0.06,0.36,0.52,0.02) | |
| Financial attraction to project investors, u18 | 0.095 | (0.00,0.00,0.01,0.25,0.10,0.60,0.04) | |
| Interest rate volatility, u19 | 0.091 | (0.00,0.00,0.01,0.23,0.32,0.44,0.00) | |
| Inflation rate volatility, u110 | 0.095 | (0.00,0.00,0.02,0.08,0.43,0.42,0.05) | |
| Legal and Socio-political risk (CRFG 2): u2 | (0.00,0.00,0.01,0.10,0.17,0.68,0.04) | ||
| Corruption and lack of respect for Law, u21 | 0.119 | (0.00,0.00,0.01,0.00,0.00,0.89,0.10) | |
| Non-involvement of the host community, u22 | 0.119 | (0.00,0.00,0.01,0.00,0.05,0.80,0.14) | |
| Poor execution of Housing Policies, u23 | 0.119 | (0.00,0.00,0.00,0.02,0.01,0.86,0.12) | |
| Wrong perception of housing need by low-income earners, u24 | 0.117 | (0.00,0.00,0.00,0.00,0.12,0.79,0.09) | |
| Illegal Title to Land, u25 | 0.117 | (0.00,0.00,0.00,0.01,0.09,0.86,0.04) | |
| Poor decision making process, u26 | 0.106 | (0.00,0.00,0.05,0.06,0.36,0.53,0.00) | |
| Change in Government, u27 | 0.189 | (0.00,0.00,0.01,0.18,0.36,0.45,0.00) | |
| Land Grabbing/Encroachment, u28 | 0.097 | (0.00,0.00,0.00,0.36,0.35,0.26,0.03) | |
| Public opposition to the mass housing projects, u29 | 0.103 | (0.00,0.00,0.06,0.27,0.13,0.48,0.06) | |
| Operation and Organization risk (CRFG 3): u3 | (0.00,0.01,0.01,0.06,0.25,0.67,0.00) | ||
| Inadequate experience in PPP, u31 | 0.208 | (0.00,0.03,0.01,0.00,0.13,0.82,0.01) | |
| Inadequate distribution of responsibility and risks, u32 | 0.199 | (0.01,0.02,0.02,0.03,0.18,0.73,0.00) | |
| Risk regarding Pricing of Product/service, u33 | 0.203 | (0.00,0.00,0.00,0.09,0.21,0.70,0.00) | |
| Lack of Commitment from Public/Private Partners, u34 | 0.197 | (0.00,0.00,0.00,0.13,0.27,0.60,0.00) | |
| Inadequate distribution of Authority between Partners, u35 | 0.193 | (0.00,0.00,0.02,0.06,0.47,0.45,0.00) | |
| Design and Project Selection risk (CRFG 4): u4 | (0.00,0.01,0.02,0.05,0.22,0.59,0.11) | ||
| Land acquisition and Site availability, u41 | 0.261 | (0.00,0.05,0.02,0.00,0.07,0.61,0.25) | |
| Level of Demand for the mass housing projects, u42 | 0.257 | (0.00,0.00,0.02,0.07,0.07,0.73,0.11) | |
| Prolonged negotiation period prior to initiation, u43 | 0.245 | (0.00,0.00,0.05,0.01,0.28,0.66,0.00) | |
| Delay in Project approvals and permits, u44 | 0.236 | (0.00,0.00,0.00,0.12,0.49.0.33,0.06) | |
| Construction risk (CRFG 5): u5 | (0.01,0.00,0.00,0.09,0.51,0.38,0.01) | ||
| Construction time delay, u51 | 0.341 | (0.00,0.00,0.00,0.09,0.42,0.49,0.00) | |
| Construction cost overrun, u52 | 0.332 | (0.00,0.00,0.00,0.09,0.57,0.34,0.00) | |
| Force majeure, u53 | 0.327 | (0.02,0.00,0.01,0.08,0.55,0.30,0.04) | |