Evaluation of the Critical risk factors in PPP - procured Mass Housing Projects in Abuja Nigeria - A fuzzy synthetic evaluation (FSE) approach

World Journal of Civil Engineering and Architecture | Vol 2, Issue 1

Table 2. Factor Reduction (Analysis) for Risk Variables in PPP ProcuredMass Housing Projects.


Risk FactorsRisk ProbabilityStd. DeviationRisk SeverityStd. DeviationRisk impactNormalized ValueRankRisk Criticality

Availability of Finance6.600.8556.540.5446.571.001Extremely High
High Finance cost6.270.7406.220.5406.250.872Very High
Corruption and lack of respect for Law6.060.4466.030.4086.040.783Very High
Non-involvement of the host community6.060.5445.900.5675.980.764Very High
Poor execution of Housing Policies6.060.4715.880.5165.970.755Very High
Wrong perception of housing need by low-income earners5.970.4625.980.3055.970.756Very High
Illegal Title to Land5.940.4185.900.3975.920.737Very High
Land acquisition and Site availability5.911.1555.920.4885.910.738Very High
Level of Demand for the mass housing projects5.820.8085.830.4585.830.699Very High
Inadequate experience in PPP5.750.7495.790.5125.770.6710Very High
Unstable Value of Local Currency5.780.4715.680.5665.730.6511Very High
Lack of creditworthiness5.670.7875.680.6905.670.6312Very High
Inadequate distribution of responsibility and risks5.530.9875.760.6445.640.6213Very High
Risk regarding Pricing of Product/service5.620.6395.570.6825.590.6014Very High
Lack of Commitment from Public/Private Partners5.470.7175.600.6235.530.5715Very High
Prolonged negotiation period prior to initiation5.550.7585.480.5865.520.5616Very High
Construction time delay5.390.6585.620.5115.500.5617Very High
Influential Economic Events (Boom/Recession)5.550.9165.410.7855.480.5518High
High Bidding cost5.520.7655.380.8485.450.5419High
Poor Financial Market5.430.7925.460.9635.450.5420High
Inadequate distribution of Authority between Partners5.340.6955.510.7655.430.5321High
Poor decision-making process5.380.8005.450.6045.410.5222High
Financial attraction to project investors5.400.9425.361.0475.380.5123High
Construction cost overrun5.260.6025.500.5675.380.5124High
Force majeure5.170.9575.541.0335.360.5025High
Delay in Project approvals and permits5.340.7685.340.6415.340.5026High
Interest rate volatility5.190.8245.470.7605.330.5027High
Change in Government5.240.7885.301.0735.270.5028High
Inflation rate volatility5.390.8025.060.9925.220.5029High
Land Grabbing/Encroachment4.950.8525.520.7705.220.5030High
Public opposition to the mass housing projects5.221.0885.151.2865.190.5031High
Weather5.110.8715.081.0925.090.3932High
Operation cost overrun5.050.6585.040.7165.050.3733High
Organization and Coordination risk4.900.9754.920.8054.910.3134High
Inability to service debt4.810.8134.990.8954.900.3135High
The bankruptcy of the investors (OPS)4.720.8834.871.0284.790.2736High
Operational revenue below the projection4.690.6224.800.7194.740.2537High
Lack of tradition of private provision of public services4.741.1574.700.9994.720.2338High
Inconsistencies in Government Policies4.680.7114.661.1054.670.2239High
Excessive contract variation4.430.7154.930.8324.680.2240High
Competition risk4.740.6184.550.8374.640.2041High
Different working methods/know-how between partners4.540.7894.750.7814.640.2042High
Environment4.640.6814.670.6394.660.2143High
Insolvency/default of Subcontractors and Suppliers4.250.6555.020.8734.620.1944High
Third party tort liability4.570.6574.610.6924.590.1845High
Availability of appropriate labour/material4.450.7634.640.9124.540.1646High
Lack of Government guarantee4.391.0014.701.0914.540.1647High
Low operating productivity 4.410.8234.590.6194.500.1448High
Rate of Return restrictions4.390.9404.601.1774.490.1449Moderate
Legislation change/Inconsistencies4.280.7154.680.8614.470.1350Moderate
Design deficiencies4.470.9434.401.1504.430.1251Moderate
Geotechnical conditions4.120.8954.790.9464.450.1252Moderate
Residual value (After concession period)4.470.7644.380.7714.420.1153Moderate
Change in tax regulation4.500.7954.291.0164.400.1054Moderate
Import and Export restriction4.190.6454.490.6254.330.0855Moderate
Possible expropriation/nationalization of assets4.120.7554.600.9124.350.0856Moderate
Industrial regulation change4.330.7264.300.7554.320.0757Moderate
Unproven Engineering techniques4.200.7194.450.6944.320.0758Moderate
Poor Quality of Workmanship4.120.7544.480.8144.300.0659Moderate
Cultural differences between the main Stakeholders4.271.1594.231.1894.250.0460Moderate
Staff crises4.110.6864.360.5894.230.0361Moderate
Strong Political opposition4.210.6854.140.9134.170.0162Moderate
Late design changes4.000.8514.301.0414.150.0063Moderate